Problem
The business needed to identify spare resource and use it effectively before taking on additional cost.
Identifying spare resource so it can be used before adding more cost
The business needed to identify spare resource and use it effectively before taking on additional cost.
I combined CargoWise, PeopleHR and Viva Insights to show activity, working patterns, contracted hours, absence, cost and future capacity.
When one department lost an employee, available resource elsewhere was moved to support it instead of immediately replacing the role.
The purpose of the report was to identify spare resource so it could be used effectively rather than taking on additional cost. It was not built to monitor individual employees.
Management and HR also needed to see where capacity could become stretched, understand the cost of unused resource and recognise periods when absence might place more pressure on a branch or department.
The report combines three real business sources:
Provides activity and additional business data. An SQL query extracts and transforms the required data before a Fabric pipeline ingests it.
Provides contracted hours, holiday data for forward capacity and absence data.
Provides Microsoft activity data used alongside the operational information.
Where the sources needed to be connected, user email addresses provided a consistent way to join the data. The combined model then supports productivity, benchmarks, cost utilisation, future capacity and absence reporting.

Capacity % =
DIVIDE(
SUM(ActivityMerged[Total Active]),
SUM(ActivityMerged[Contract Mins]),
0)

Turning unused capacity into a cost gives Management more context than a percentage alone. It shows where existing resource could potentially be used before more cost is added elsewhere.
Unutilised % =
1 - [Capacity %]
Unutilised Cost =
[Salaries] * [Unutilised %]

In the test-data example, Chelmsford operates at a much lower capacity than Birmingham and Manchester. The report gives managers a reason to investigate workload and where resource could be moved.

Capacity risks for departments and branches were identified early and dealt with, reducing pressure on staff. Managers could move available resource, adjust workload or arrange cover before the problem reached the team.

High-absence months could be identified to help anticipate when absence may be high again. This helps answer practical questions: Which branch or department may be short of resource? When is pressure likely to increase? Is spare resource available elsewhere?
Absence % =
DIVIDE(
SUM(EmployeeLeave[Duration _Days_]),
[Avaliable working days],
0)
Existing resource was reallocated instead of immediately adding replacement headcount.
When a department lost an employee, the report helped identify available resource elsewhere that could be moved to support the work.
Capacity risks across departments and branches were identified earlier.
Earlier visibility allowed workload, cover or available resource to be addressed before the situation placed additional pressure on staff.
Higher-absence periods could be anticipated more effectively.
Historical absence patterns helped show when absence and capacity pressures were more likely, supporting earlier planning and questions about where resource might become stretched.